Step 3: Wait for approval
We will contact you within four weeks of
receiving your application. If your application is successful, BC
Housing will confirm the approved adaptations, the maximum value of
your grant or loan, and the terms and conditions of your
participation in the program. At this point we will also give
approval for you to begin work.
You will have 90 days to complete the work from
the date of approval. If you do not complete the work by that time
and we do not hear from you, your assistance may be cancelled.
Funds are limited and we have an obligation to reimburse work
completed within the expected time frames.
Common reasons for not approving or cancelling an
application include:
-
Not all of the eligibility criteria were satisfied
-
The application is incomplete
-
The application has lapsed
-
Funding is no longer available
Appeals: If your application is not approved and
you wish to dispute the decision, you must submit in writing your
reasons for appeal within 30 days of the date of the rejection
letter. You will need to submit an appeal with all supporting and
required documents. If you are a tenant, your landlord must submit
the appeal.
Home Adaptations for Independence Program
BC Housing
Homeowner Protection Branch
Suite 650 – 4789 Kingsway
Burnaby, BC V5H 0A3
Email: hafi@bchousing.org
Fax: 604-646-7054
BC Housing
Homeowner Protection Branch
Suite 650 – 4789 Kingsway
Burnaby, BC V5H 0A3
Email: hafi@bchousing.org
Fax: 604-646-7054