The Act gives you the right to ask contractors for a Statutory
Declaration confirming they have paid their bills. BC Housing
requires contractors to submit a Statutory Declaration Form 9A for
second and subsequent payment draws and when requesting release of
the lien holdback.
The lien holdback must be paid 55 days after the contractor
declares substantial performance, provided no liens have been
filed. Conduct a lien search before making the payment. The
contractor is confirming bills have been paid when the Statutory
Declaration is signed, which will limit your liability for unpaid
contractor accounts. See page 13 in chapter three of the
Maintenance Guide for more information on lien searches